The term "Force Majeure" has been replaced with (Clause 18). While the legal substance remains similar—covering events beyond a party's control like war, terrorism, or natural disasters—the new phrasing is intended to be more universally understood across different legal jurisdictions (Civil vs. Common Law). Conclusion: Staying Updated
The release of the (Red, Yellow, and Silver Books) marked the most significant update to international construction standard forms in nearly two decades. For practitioners seeking a FIDIC 2017 practical legal guide (PDF updated) , understanding the shift toward increased prescription, enhanced dispute avoidance, and rigorous procedural requirements is essential for project success. fidic 2017 a practical legal guide pdf updated
Under the 2017 Suite, the Engineer is no longer just a project manager; they are a proactive "facilitator." The term "Force Majeure" has been replaced with (Clause 18)
Failure to provide notice within 28 days results in the claim being time-barred, and the other party is discharged from any liability. Conclusion: Staying Updated The release of the (Red,