Saudi Aramco Schedule G -

Saudi Aramco's is a foundational contract document that outlines the strict policies, responsibilities, and management protocols for materials, tools, and equipment used in projects. For any contractor or supplier working with the global energy giant, mastering Schedule G is essential for operational compliance and successful project delivery. 1. Scope and Core Definitions

Contractors are required to prioritize Saudi manufacturers, vendors, and carriers over international options. saudi aramco schedule g

Unused or reusable materials must be returned to Aramco in "as good" condition, typically at the contractor's expense. 3. Procurement and "In-Kingdom Total Value Add" (iktva) Saudi Aramco's is a foundational contract document that

Contractors must implement a Materials Management System to track receipt, usage, damage, and remaining stock. Scope and Core Definitions Contractors are required to

For items exceeding $10,000 , contractors must typically obtain at least three quotes from Saudi manufacturers and provide a cost comparison to Aramco before finalizing a purchase.

Schedule G serves as the primary governing document for how physical assets—ranging from massive steel pipelines to specialized construction tools—are sourced, tracked, and maintained. It distinguishes clearly between two categories of assets: